在以下哪种合同中,更容易进行合同范围变更? In which of the following contract type is it easier to change the scope of the contract?
A: 1、固定价Firm Fixed Price
B: 2、固定价加激励费Fixed Price Plus Incentive Fee
C: 3、成本加成本百分比Cost Plus Percentage of Cost
D: 4、以上都不是None of the above
A: 1、固定价Firm Fixed Price
B: 2、固定价加激励费Fixed Price Plus Incentive Fee
C: 3、成本加成本百分比Cost Plus Percentage of Cost
D: 4、以上都不是None of the above
举一反三
- 下列合同类型中,卖方承担的风险最大 A: Cost plus percentage of costs:成本加成本百分比 B: Cost plus fixed fee:成本加固定费 C: Cost Plus Incentive Fee:成本加奖金 D: Firm Fixed Price :固定价格
- According to ( ) classification, the project contract can be generally divided into total price contract, unit price contract and cost plus remuneration contract. A: Job content B: Contract scope C: Project deadline D: Payment method
- Who has the highest cost risk in case of a fixed price contract ?() A: Buye B: Selle C: Sponso D: Tea
- Which of the following is NOT a method of transfer pricing? A: Cost plus transfer price B: Internal price C: Market-based transfer price D: Two part transfer price
- 在___合同中, 卖方最关心项目范围 A: 固定定价 B: 成本加固定费 C: 时间和材料 D: 成本加基本费