The payback period of the project refers to项目的投资回收期是指()。
A: Time required to repay all loans of the project 还清项目所有贷款所需的时间
B: The time from the beginning of the project to the time point of the cumulative profit of the project equals to the project cost 从项目开始到项目获得的累计利润等于项目成本所需的时间
C: Time required for the company to obtain sufficient funds to start the project 公司为启动项目而取得足够的资金所需要的时间
D: Time required for the company to recover equity investment after the project is put into operation在项目投产后,公司收回股权投资所需的时间
A: Time required to repay all loans of the project 还清项目所有贷款所需的时间
B: The time from the beginning of the project to the time point of the cumulative profit of the project equals to the project cost 从项目开始到项目获得的累计利润等于项目成本所需的时间
C: Time required for the company to obtain sufficient funds to start the project 公司为启动项目而取得足够的资金所需要的时间
D: Time required for the company to recover equity investment after the project is put into operation在项目投产后,公司收回股权投资所需的时间
举一反三
- The close project process is a part of which of the following project management knowledge areas ?() A: project scope managemen B: project integration managemen C: project time managemen D: project communication managemen
- ____ project(次要项目)
- ● (74) is primarily concerned with defining and controlling what is and is not included in the project. (74) A. Project Time Management B. Project Cost Management C. Project Scope management D. Project Communications Management
- It will take time and money to get the project to ________________ .
- 执行菜单命令(),系统开始对项目进行编译,并生成信息报告 A: project/compile PCB project B: project/project option C: Design/netlist/protel D: design/make project library