Earned value technique is used in which process ?()
A: Direct and manage project executio
B: Monitor and control project wor
C: Integrated change contro
D: Develop project management pla
A: Direct and manage project executio
B: Monitor and control project wor
C: Integrated change contro
D: Develop project management pla
举一反三
- The process is primarily concerned with authorizing the project or, in a multiphase project, a project phase is called ______ . A: develop project charter B: develop prepliminary project scope statement C: management review D: phase-end review
- Your project has a number of different work results.You are collecting information about these work results,such as what costs have been incurred or committed and which deliverables have been completed and which remain outstanding.You will use this information in which of the following processes A: Project plan executio B: Integrated change contro C: Report performanc D: Verify scop
- The close project process is a part of which of the following project management knowledge areas ?() A: project scope managemen B: project integration managemen C: project time managemen D: project communication managemen
- Configuration management is a technique for______. A: overall change control B: project plan execution C: scope planning D: risk quantification
- Project manager believes that modifying the project scope may provide added value for the customer.the project manager should(). A: change the scopr baseline B: contact the customer to determine if the change adds value C: call a meeting of the change control board D: change the project's objectives