    Earned value technique is used in which process ?()
    A: Direct and manage project executio
    B: Monitor and control project wor
    C: Integrated change contro
    D: Develop project management pla
  • B

    内容

    • 0

      The Program Evaluation Review Technique (PERT) of project management is used for ______. A: A) project planning and predicting B: B) developing cost histograms C: C) providing visibility and enabling management to control one of a kind projects D: D) both A and C

    • 1

      All of followings should be done by the project manager during project control except ______. A: Determine the a change has occurred B: Ensure that a change is agreed C: Make sure all changes are approved by management D: Manage changes as they occur

    • 2

      The project charter is created in which project management process group ?() A: Executing B: Planning C: Closing D: Initiating

    • 3

      You are the project manager responsible for developing a software application based on customer requirements.As the customer requirements keep changing frequently,what tool can you use to conduct integrated change control of your project ?() A: Project selection methods B: Additional planning C: Corrective action D: Project management information system

    • 4

      You are the project manager responsible for developing a software application based on customer requirements.As the customer requirements keep changing frequently,what tool can you use to conduct integrated change control of your project ?() A: Project selection method B: Additional plannin C: Corrective actio D: Project management information syste