When should lessons learned be organized ?()
A: During the project life cycle and at the en
B: At the end of the project during closin
C: After the end of the project at a project post-mortem meetin
D: Lessons learned can be organized when there is time availabl
A: During the project life cycle and at the en
B: At the end of the project during closin
C: After the end of the project at a project post-mortem meetin
D: Lessons learned can be organized when there is time availabl
举一反三
- The most crucial time for project risk assessment is______. A: when a problem surfaces B: during the planning phase C: during the close-out phase D: after the project schedule has been published
- Which of the following statements is true?( ) A: Knowledge is commonly split into “explicit” and “tacit” . B: Managing knowledge involves just documenting it so it can be shared. C: Managing knowledge involves just obtaining lessons learned at the end of the project, in order to use it in the future projects. D: Knowledge and information management tools and techniques should be connected to project processes and process owners.
- The most crucial time for project risk assessment is ______。 A: when a problem surfaces B: during the planning phase C: during the close-out phase D: after the pr03iect schedule has been published
- Project Initiation is the first phase in the project management life cycle .
- 中国大学MOOC: You can usually expect there to be some sort of project or test at the end of each section to reinforce what was learned in that section or week.