A project control system ______.
A: monitors and controls the project’s schedule, costs, scope, budgets, etc.
B: is a mechanism which reacts to the current project status in order to ensure accomplishment of project objectives
C: is only needed on large "mega" projects
D: is a system for controlling and executing project documentation in a uniform and timely manner
A: monitors and controls the project’s schedule, costs, scope, budgets, etc.
B: is a mechanism which reacts to the current project status in order to ensure accomplishment of project objectives
C: is only needed on large "mega" projects
D: is a system for controlling and executing project documentation in a uniform and timely manner
举一反三
- Project manager believes that modifying the project scope may provide added value for the customer.the project manager should(). A: change the scopr baseline B: contact the customer to determine if the change adds value C: call a meeting of the change control board D: change the project's objectives
- The close project process is a part of which of the following project management knowledge areas ?() A: project scope managemen B: project integration managemen C: project time managemen D: project communication managemen
- All the following are benefits of fast tracking a project EXCEPT ______ . A: facilitates duration compression B: reduces risk C: ensure activities are done in parallel which would normally be done in sequence D: helps shorten the project schedule without changing the project scope
- The project life-cycle can be described as ( ). A: project concept, project planning, project execution, and project close-out B: project planning, work authorization,and project reporting C: project planning, project control, project definition, WBS development , and project termination D: project concept,project execution, and project reporting
- ● (74) is primarily concerned with defining and controlling what is and is not included in the project. (74) A. Project Time Management B. Project Cost Management C. Project Scope management D. Project Communications Management