All the following are benefits of fast tracking a project EXCEPT ______ .
A: facilitates duration compression
B: reduces risk
C: ensure activities are done in parallel which would normally be done in sequence
D: helps shorten the project schedule without changing the project scope
A: facilitates duration compression
B: reduces risk
C: ensure activities are done in parallel which would normally be done in sequence
D: helps shorten the project schedule without changing the project scope
举一反三
- All of followings should be done by the project manager during project control except ______. A: Determine the a change has occurred B: Ensure that a change is agreed C: Make sure all changes are approved by management D: Manage changes as they occur
- A project control system ______. A: monitors and controls the project’s schedule, costs, scope, budgets, etc. B: is a mechanism which reacts to the current project status in order to ensure accomplishment of project objectives C: is only needed on large "mega" projects D: is a system for controlling and executing project documentation in a uniform and timely manner
- The close project process is a part of which of the following project management knowledge areas ?() A: project scope managemen B: project integration managemen C: project time managemen D: project communication managemen
- In your project, you are in the process of determining whether the activities being done as part of your project comply with organizational and project policies. This will be done as part of ______ . A: A) inspection B: B) quality audit C: C) quality improvement D: D) trend analysis
- A project manager has just been assigned to a new project and has been given the project charter. The FIRST thing the project manager must do is______. A: A) create a project scope statement B: B) confirm that all the stakeholders have had input into the scope C: C) analyze project risk D: D) begin work on a project management plan