When should a project baseline be changed
A: A) When a major delay occurs.
B: B) When an official change is made.
C: C) When a cost increase occurs.
D: D) Changes should never be made in the baseline.
A: A) When a major delay occurs.
B: B) When an official change is made.
C: C) When a cost increase occurs.
D: D) Changes should never be made in the baseline.
举一反三
- When should the project baseline be changed A: A) It should not he changed. B: B) Only for changes that have been approved by the change control board. C: C) At each project team meeting. D: D) For all implemented changes.
- ____(警惕的) decision making occurs when people believe that (1) a choice should be made, (2) they can find a solution, and (3) there is enough time.
- When cancellation occurs, clerks should adjust the reservation report accordingly.
- when a major family relationship problem occurs, some people try to get the other person to change. Sometimes this works, especially when .
- 44.The writer of the passage advises that further risk assessment should be made when ________.