When should the project baseline be changed
A: A) It should not he changed.
B: B) Only for changes that have been approved by the change control board.
C: C) At each project team meeting.
D: D) For all implemented changes.
A: A) It should not he changed.
B: B) Only for changes that have been approved by the change control board.
C: C) At each project team meeting.
D: D) For all implemented changes.
举一反三
- When should a project baseline be changed A: A) When a major delay occurs. B: B) When an official change is made. C: C) When a cost increase occurs. D: D) Changes should never be made in the baseline.
- All of followings should be done by the project manager during project control except ______. A: Determine the a change has occurred B: Ensure that a change is agreed C: Make sure all changes are approved by management D: Manage changes as they occur
- Project manager believes that modifying the project scope may provide added value for the customer.the project manager should(). A: change the scopr baseline B: contact the customer to determine if the change adds value C: call a meeting of the change control board D: change the project's objectives
- A project manager has made a change to the project. What should he do next A: A) Assign resource. B: B) Revise the project plan. C: C) Evaluate impact. D: D) Request change control board involvement.
- I kept this seat for him in case he ( )()( ) this mind. A: change B: changed C: changes D: has changed