What does a negative Schedule Variance indicate A: The project is behind in the schedule. B: Up-scope is causing cost overruns. C: The project is ahead of schedule. D: The project is on schedule.
What does a negative Schedule Variance indicate A: The project is behind in the schedule. B: Up-scope is causing cost overruns. C: The project is ahead of schedule. D: The project is on schedule.