If the project completion time is normally distributed and the due date for the project is greater than the expected completion time, then the probability that the project will be finished by the due date is A: a. less than 0.50. B: b. greater than 0.50. C: c. equal to 0.50. D: d. undeterminable without more information.
If the project completion time is normally distributed and the due date for the project is greater than the expected completion time, then the probability that the project will be finished by the due date is A: a. less than 0.50. B: b. greater than 0.50. C: c. equal to 0.50. D: d. undeterminable without more information.