Which of the following is the best use of lessons learned ?()
A: Planning record for the current projec
B: To impress the senior managemen
C: Informing the team about what mistakes team has mad
D: Historical information for future project
A: Planning record for the current projec
B: To impress the senior managemen
C: Informing the team about what mistakes team has mad
D: Historical information for future project
举一反三
- The close project process is a part of which of the following project management knowledge areas ?() A: project scope managemen B: project integration managemen C: project time managemen D: project communication managemen
- Which of the following statements is true?( ) A: Knowledge is commonly split into “explicit” and “tacit” . B: Managing knowledge involves just documenting it so it can be shared. C: Managing knowledge involves just obtaining lessons learned at the end of the project, in order to use it in the future projects. D: Knowledge and information management tools and techniques should be connected to project processes and process owners.
- A team member notices the project manager that a quality measurement for the project can not be met. What should the project manager do A: Notify managemen B: Hold a team meetin C: Look for alternative ways to meet the quality leve D: Ask management tp come up with option
- Your project has a number of different work results.You are collecting information about these work results,such as what costs have been incurred or committed and which deliverables have been completed and which remain outstanding.You will use this information in which of the following processes A: Project plan executio B: Integrated change contro C: Report performanc D: Verify scop
- Your project has a number of different work results. You are collecting information about these work results such as what costs have been incurred or committed and which deliverables have been completed and which remain outstanding. You will use this information in which of the following processes A: A) Direct and manage project execution. B: B) Perform integrated change control. C: C) Reprot performance. D: D) Verify scope.