    Which of the following is false? ( )
    A: Contingency is not a substitute for proper cost estimating
    B: Contingency should be included in Base Estimates in budgets, cost plans or forecasts
    C: An undesirable event that is highly likely to occur should be included in the Base Estimate, not in contingency
    D: The calculation of contingency should align with the project risk profile