The Estimate Activity Resource process is closely coordinated with the (73)process. (73) A. Estimate Costs B. Sequence Activities C. Plan Communications D. Conduct Procurements
举一反三
- Communications is the process of transmitting a message from a(n) to an audience via a channel. A: root B: resource C: origin D: source
- The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estimated resource quantities,and resource calendars with resource availabilities. A.estimating B.defining C.planning D.sequencing
- Account analysis approach is particularly useful to estimate mixed costs when no past experience is available concerning activity and costs. A: 正确 B: 错误
- Which of the following is included in a project charter ?() A: Identification of risk B: Work package estimate C: Detailed resource estimate D: The business need for the projec