Which of the following is included in a project charter ?()
A: Identification of risk
B: Work package estimate
C: Detailed resource estimate
D: The business need for the projec
A: Identification of risk
B: Work package estimate
C: Detailed resource estimate
D: The business need for the projec
举一反三
- Why is it important to have a project charter ?() A: It is the collection of all subsidiary project document B: The project charter is the necessary basis for all work packages to be performe C: It formally authorizes the projec D: It tracks the progress of the projec
- Which of the following is false? ( ) A: Contingency is not a substitute for proper cost estimating B: Contingency should be included in Base Estimates in budgets, cost plans or forecasts C: An undesirable event that is highly likely to occur should be included in the Base Estimate, not in contingency D: The calculation of contingency should align with the project risk profile
- Inputs to determine budget include all of the following EXCEPT (). A: cost baseline B: cost estimate C: work breakdown structure D: project schedule
- Inputs to determine budget include all of the following EXCEPT ______ . A: A) cost baseline B: B) cost estimate C: C) work breakdown structure D: D) project schedule
- Which of the following points should be included in a feasibility report? A: initial design,scope and materials B: preliminary cost estimate C: funding and financing D: site selection E: project background F: market analysis G: supply of equipment and materials H: conclusion