The project scope is measured against the ______, while the product scope is measured against the ______.
A: plan, requirements
B: requirements, measure of success
C: scope baseline, scope definition
D: contract, verification
A: plan, requirements
B: requirements, measure of success
C: scope baseline, scope definition
D: contract, verification
A
举一反三
- The process of choosing/documenting the best approach to achieve the project objectives is part of: A: The scope baseline. B: Scope authorization C: Scope definition D: Scope planning. E: All of the above.
- The preparation of the scope baseline involves the ______. A: functional manager B: project team C: all the stakeholders D: project sponsor
- Each person’s abilities are measured _______ the job requirements and expected tasks. A: for B: at C: in D: against
- Close procurements is similar to close project in that they both involve: A: A) Product verification. B: B) Kick off meetings. C: C) Quality assurance activities. D: D) Creation of the scope verification plan.
- A project manager has just been assigned to a new project and has been given the project charter. The FIRST thing the project manager must do is______. A: A) create a project scope statement B: B) confirm that all the stakeholders have had input into the scope C: C) analyze project risk D: D) begin work on a project management plan
内容
- 0
Configuration management is a technique for______. A: overall change control B: project plan execution C: scope planning D: risk quantification
- 1
The inputs of developing project management plan do not include(). A: project charter B: stakeholder management strategy C: project scope statement D: outputs from plamung processes
- 2
According to ( ) classification, the project contract can be generally divided into total price contract, unit price contract and cost plus remuneration contract. A: Job content B: Contract scope C: Project deadline D: Payment method
- 3
which one is not the dimension of a plan? A: repetitiveness B: scope C: time D: scheduling
- 4
在JSP中为内建对象定义了4种作用范围,即Application Scope、Session Scope、Page Scope和( )四个作用范围