Inputs used during scope planning include all of the following EXCEPT ______ .
A: constraints
B: project charter
C: budget/cost analysis
D: product description
A: constraints
B: project charter
C: budget/cost analysis
D: product description
举一反三
- Inputs to determine budget include all of the following EXCEPT (). A: cost baseline B: cost estimate C: work breakdown structure D: project schedule
- Inputs to determine budget include all of the following EXCEPT ______ . A: A) cost baseline B: B) cost estimate C: C) work breakdown structure D: D) project schedule
- The inputs of developing project management plan do not include(). A: project charter B: stakeholder management strategy C: project scope statement D: outputs from plamung processes
- The project plan is used to do all of the following EXCEPT ______. A: A) document project planning assumption B: B) define the content of management reviews C: C) identify risks that arise during project execution D: D) provide a baseline for progress measurement and project control
- Analysis of which of the following factors is carried out in Phase 2 of the international planning process? A: Situation analysis B: Budgets C: Product adaptation D: Host-country constraints E: Company character