The inputs of developing project management plan do not include().
A: project charter
B: stakeholder management strategy
C: project scope statement
D: outputs from plamung processes
A: project charter
B: stakeholder management strategy
C: project scope statement
D: outputs from plamung processes
举一反三
- The process is primarily concerned with authorizing the project or, in a multiphase project, a project phase is called ______ . A: develop project charter B: develop prepliminary project scope statement C: management review D: phase-end review
- The Develop Project Management Plan Process includes the actions necessary to define,prepare,integrate,and coordinate all constituent plans into a(75). A.Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter
- A project manager has just been assigned to a new project and has been given the project charter. The FIRST thing the project manager must do is______. A: A) create a project scope statement B: B) confirm that all the stakeholders have had input into the scope C: C) analyze project risk D: D) begin work on a project management plan
- ● (74) is primarily concerned with defining and controlling what is and is not included in the project. (74) A. Project Time Management B. Project Cost Management C. Project Scope management D. Project Communications Management
- You are assigned as a project manager to lead a new quality improvement project. Management is asking for a project management plan. Which of the following should you create FIRST A: A) A process assurance plan. B: B) A quality management plan. C: C) A project management plan. D: D) A project scope statement.