A: A) cost baseline
B: B) cost estimate
C: C) work breakdown structure
D: D) project schedule
举一反三
- Inputs to determine budget include all of the following EXCEPT ______ . A: A) cost baseline B: B) cost estimate C: C) work breakdown structure D: D) project schedule
- Inputs used during scope planning include all of the following EXCEPT ______ . A: constraints B: project charter C: budget/cost analysis D: product description
- Scope change control MUST be integrated with all of the following control processes EXCEPT ______ . A: schedule B: cost C: procurement D: quality
- Scope change control MUST be integrated with all of the following control processes EXCEPT ______ . A: A) schedule B: B) cost C: C) procurement D: D) quality
- Of the following factors, all, except ( ) , can influence the change in the supply of a particular commodity. A: technology B: the price of inputs (cost) C: expectations D: the price of the commodity itself
内容
- 0
Which of the following is not a functional budget?( ) A: Distribution cost budget B: Production budget C: Selling cost budget D: Cash budget
- 1
The Land account would include all of the following costs except( )。 A: drainage costs. B: the cost of building a fence. C: commissions paid to real estate agents. D: the cost of tearing down a building.
- 2
The evaluation index of variance analysis in EVM include ( )。 A: Schedule variance (SV) B: Cost performance index (CPI) C: Cost variance (CV) D: Project performance index (PPI)
- 3
Variance analysis include ( ) A: Schedule variance B: Cost variance C: The schedule performance index D: The cost performance index
- 4
The project plan is used to do all of the following EXCEPT ______. A: A) document project planning assumption B: B) define the content of management reviews C: C) identify risks that arise during project execution D: D) provide a baseline for progress measurement and project control