The document that officially sanctions the project is the ( )。
A: Project charter
B: Feasibility study
C: Project plan
D: Benefit/Cost analysis
A: Project charter
B: Feasibility study
C: Project plan
D: Benefit/Cost analysis
举一反三
- (Single Choice)The work of feasibility study stage of China's high-speed railway project does not include which of the following.( ) A: Project evaluation and decision B: Feasibility study C: Compilation of project proposal D: Design of construction drawing
- Why is it important to have a project charter ?() A: It is the collection of all subsidiary project document B: The project charter is the necessary basis for all work packages to be performe C: It formally authorizes the projec D: It tracks the progress of the projec
- The inputs of developing project management plan do not include(). A: project charter B: stakeholder management strategy C: project scope statement D: outputs from plamung processes
- The project charter for a project was approved for planning and you have Just been assigned as project manager.Realizing that project planning is an ongoing effort throughout the project,which processes are you MOST likely to combine ?() A: Create WBS and activity definitio B: Activity duration estimating and schedule developmen C: Human resource planning and cost estimatin D: Cost estimating and cost budgetin
- In<br/>Software Development Life Cycle, ____ is a preliminary study before<br/>the main work of a project starts, which finds out the probability of<br/>the project’s success. A: feasibility<br/>study B: requirement<br/>analysis C: implementation D: operation<br/>and maintenance