Which of the following is a direct project cost
A: Lighting and heating for the corporate office.
B: Workers compensation insurance.
C: Piping for an irrigation project.
D: A and B.
A: Lighting and heating for the corporate office.
B: Workers compensation insurance.
C: Piping for an irrigation project.
D: A and B.
举一反三
- ● (74) is primarily concerned with defining and controlling what is and is not included in the project. (74) A. Project Time Management B. Project Cost Management C. Project Scope management D. Project Communications Management
- Project X has the following cash flows: C0 = +2,000, C1 = -1,150, and C2 = -1,150. If the IRR of the project is 9.85 percent and if the cost of capital is 12.00 percent, you would A: accept the project. B: reject the project. C: do not know. D: need further information.
- You are assigned as a project manager to lead a new quality improvement project. Management is asking for a project management plan. Which of the following should you create FIRST A: A) A process assurance plan. B: B) A quality management plan. C: C) A project management plan. D: D) A project scope statement.
- The close project process is a part of which of the following project management knowledge areas ?() A: project scope managemen B: project integration managemen C: project time managemen D: project communication managemen
- Roman Aqueduct is a project for irrigation