You are assigned as the project manager in the middle of the project. The project is within the baselines, but the customer is not happy with the performance of the project. What is the FIRST thing you should do () A: Discuss it with the project team. B: Recalculate baselines. C: Renegotiate the contract. D: Meet with the customer.
You are assigned as the project manager in the middle of the project. The project is within the baselines, but the customer is not happy with the performance of the project. What is the FIRST thing you should do () A: Discuss it with the project team. B: Recalculate baselines. C: Renegotiate the contract. D: Meet with the customer.
● (74) is primarily concerned with defining and controlling what is and is not included in the project. (74) A. Project Time Management B. Project Cost Management C. Project Scope management D. Project Communications Management
● (74) is primarily concerned with defining and controlling what is and is not included in the project. (74) A. Project Time Management B. Project Cost Management C. Project Scope management D. Project Communications Management
The project is on the point of collapse, and unless something very ________ is done to repair the damage there will be no hope for the project.
The project is on the point of collapse, and unless something very ________ is done to repair the damage there will be no hope for the project.
4.4 The more markets an entrepreneurial project can serve, the greater the success possibility of the entrepreneurial project.( )
4.4 The more markets an entrepreneurial project can serve, the greater the success possibility of the entrepreneurial project.( )
Project X has the following cash flows: C0 = +2,000, C1 = -1,150, and C2 = -1,150. If the IRR of the project is 9.85 percent and if the cost of capital is 12.00 percent, you would A: accept the project. B: reject the project. C: do not know. D: need further information.
Project X has the following cash flows: C0 = +2,000, C1 = -1,150, and C2 = -1,150. If the IRR of the project is 9.85 percent and if the cost of capital is 12.00 percent, you would A: accept the project. B: reject the project. C: do not know. D: need further information.
()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.
()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.
You are assigned as a project manager to lead a new quality improvement project. Management is asking for a project management plan. Which of the following should you create FIRST A: A) A process assurance plan. B: B) A quality management plan. C: C) A project management plan. D: D) A project scope statement.
You are assigned as a project manager to lead a new quality improvement project. Management is asking for a project management plan. Which of the following should you create FIRST A: A) A process assurance plan. B: B) A quality management plan. C: C) A project management plan. D: D) A project scope statement.
A project manager has made a change to the project. What should he do next A: A) Assign resource. B: B) Revise the project plan. C: C) Evaluate impact. D: D) Request change control board involvement.
A project manager has made a change to the project. What should he do next A: A) Assign resource. B: B) Revise the project plan. C: C) Evaluate impact. D: D) Request change control board involvement.
Which of the following is a direct project cost A: Lighting and heating for the corporate office. B: Workers compensation insurance. C: Piping for an irrigation project. D: A and B.
Which of the following is a direct project cost A: Lighting and heating for the corporate office. B: Workers compensation insurance. C: Piping for an irrigation project. D: A and B.
(Single Choice)In the project management of railway construction, which of the following is the mode of contracting according to the quantity of project.( ) A: The lump-sum contracting mode B: The construction management mode C: The general project contracting mode D: The unit price contracting mode
(Single Choice)In the project management of railway construction, which of the following is the mode of contracting according to the quantity of project.( ) A: The lump-sum contracting mode B: The construction management mode C: The general project contracting mode D: The unit price contracting mode