You are assigned as a project manager to lead a new quality improvement project. Management is asking for a project management plan. Which of the following should you create FIRST
A: A) A process assurance plan.
B: B) A quality management plan.
C: C) A project management plan.
D: D) A project scope statement.
A: A) A process assurance plan.
B: B) A quality management plan.
C: C) A project management plan.
D: D) A project scope statement.
举一反三
- The project team has created a plan for how they will implement the quality policy. If this changes during the project, it will also be a change to ______. A: the project plan B: the quality control plan C: the quality assurance plan D: the quality management plan
- A project manager has just been assigned to a new project and has been given the project charter. The FIRST thing the project manager must do is______. A: A) create a project scope statement B: B) confirm that all the stakeholders have had input into the scope C: C) analyze project risk D: D) begin work on a project management plan
- The inputs of developing project management plan do not include(). A: project charter B: stakeholder management strategy C: project scope statement D: outputs from plamung processes
- The Develop Project Management Plan Process includes the actions necessary to define,prepare,integrate,and coordinate all constituent plans into a(75). A.Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter
- You prepared an integrated project plan and a project schedule.You submitted it to the steering committee,and it was approved.Key stakeholders accepted the plan.It is time to distribute it.Both the project plan and schedule should be distributed to______. A: all stakeholders in the performing organization B: all project stakeholders C: project team members and the project sponsor D: people noted in the communications management plan