You are assigned as the project manager in the middle of the project.The project is within the baselines,but the customer is not happy with the performance of the project.What is the FIRST thing you should do ?() A: Discuss it with the project tea B: Recalculate baseline C: Renegotiate the contrac D: Meet with the custome
You are assigned as the project manager in the middle of the project.The project is within the baselines,but the customer is not happy with the performance of the project.What is the FIRST thing you should do ?() A: Discuss it with the project tea B: Recalculate baseline C: Renegotiate the contrac D: Meet with the custome