    Project manager believes that modifying the project scope may provide added value for the customer.the project manager should(). A: change the scopr baseline B: contact the customer to determine if the change adds value C: call a meeting of the change control board D: change the project's objectives

    Project manager believes that modifying the project scope may provide added value for the customer.the project manager should(). A: change the scopr baseline B: contact the customer to determine if the change adds value C: call a meeting of the change control board D: change the project's objectives