The Program Evaluation Review Technique (PERT) of project management is used for ______.
A: A) project planning and predicting
B: B) developing cost histograms
C: C) providing visibility and enabling management to control one of a kind projects
D: D) both A and C
A: A) project planning and predicting
B: B) developing cost histograms
C: C) providing visibility and enabling management to control one of a kind projects
D: D) both A and C
举一反三
- Which of the following techniques is used for tracking the project risks?() A: Probability-Impact matrix B: Pareto chart C: R-Chart D: PERT (Program Evaluation and Review Technique) analysis
- Configuration management is a technique for______. A: overall change control B: project plan execution C: scope planning D: risk quantification
- Earned value technique is used in which process ?() A: Direct and manage project executio B: Monitor and control project wor C: Integrated change contro D: Develop project management pla
- The project plan is used to do all of the following EXCEPT ______. A: A) document project planning assumption B: B) define the content of management reviews C: C) identify risks that arise during project execution D: D) provide a baseline for progress measurement and project control
- Project management techniques applied to ongoing operations is called as ______ . A: portfolio management B: management by projects C: management by objectives D: management by exception