    The Program Evaluation Review Technique (PERT) of project management is used for ______.
    A: A) project planning and predicting
    B: B) developing cost histograms
    C: C) providing visibility and enabling management to control one of a kind projects
    D: D) both A and C
  • D

    内容

    • 0

      ( ) is the core of project managementQuality management. A: Cost management B: Contract management C: Quality management D: Schedule management

    • 1

      The inputs of developing project management plan do not include(). A: project charter B: stakeholder management strategy C: project scope statement D: outputs from plamung processes

    • 2

      ● (74) is primarily concerned with defining and controlling what is and is not included in the project. (74) A. Project Time Management B. Project Cost Management C. Project Scope management D. Project Communications Management

    • 3

      The process is primarily concerned with authorizing the project or, in a multiphase project, a project phase is called ______ . A: develop project charter B: develop prepliminary project scope statement C: management review D: phase-end review

    • 4

      You are the project manager responsible for developing a software application based on customer requirements.As the customer requirements keep changing frequently,what tool can you use to conduct integrated change control of your project ?() A: Project selection methods B: Additional planning C: Corrective action D: Project management information system