In your project,you have created performance reports to provide the status and progress information to different stakeholders.The results from the performance reports should be compared to the______.
A: project management plan
B: performance measurement baseline
C: earned value calculations
D: none of the above
A: project management plan
B: performance measurement baseline
C: earned value calculations
D: none of the above
举一反三
- Examples of work performance reports include status reports and progress reports.
- Performance reports compare actual results to ________. Performance reports also report ________.
- The project plan is used to do all of the following EXCEPT ______. A: A) document project planning assumption B: B) define the content of management reviews C: C) identify risks that arise during project execution D: D) provide a baseline for progress measurement and project control
- You are a project manager who was just assigned to take over a project from another project manager who is leaving the company. The old project manager tells you that the project is on schedule only because he has had to constantly push the team to perform. What is the FIRST thing you should do as the new project manager ?() A: Check risk status B: Check cost performance C: Determine a management strategy D: Tell the team your objectives
- You are assigned as the project manager in the middle of the project.The project is within the baselines,but the customer is not happy with the performance of the project.What is the FIRST thing you should do ?() A: Discuss it with the project tea B: Recalculate baseline C: Renegotiate the contrac D: Meet with the custome