You are a project manager who was just assigned to take over a project from another project manager who is leaving the company. The old project manager tells you that the project is on schedule only because he has had to constantly push the team to perform. What is the FIRST thing you should do as the new project manager ?()
A: Check risk status
B: Check cost performance
C: Determine a management strategy
D: Tell the team your objectives
A: Check risk status
B: Check cost performance
C: Determine a management strategy
D: Tell the team your objectives
举一反三
- A project manager has just been assigned to a new project and has been given the project charter. The FIRST thing the project manager must do is______. A: A) create a project scope statement B: B) confirm that all the stakeholders have had input into the scope C: C) analyze project risk D: D) begin work on a project management plan
- You are assigned as the project manager in the middle of the project. The project is within the baselines, but the customer is not happy with the performance of the project. What is the FIRST thing you should do () A: Discuss it with the project team. B: Recalculate baselines. C: Renegotiate the contract. D: Meet with the customer.
- You are assigned as the project manager in the middle of the project.The project is within the baselines,but the customer is not happy with the performance of the project.What is the FIRST thing you should do ?() A: Discuss it with the project tea B: Recalculate baseline C: Renegotiate the contrac D: Meet with the custome
- You are assigned as a project manager to lead a new quality improvement project. Management is asking for a project management plan. Which of the following should you create FIRST A: A) A process assurance plan. B: B) A quality management plan. C: C) A project management plan. D: D) A project scope statement.
- A team member notices the project manager that a quality measurement for the project can not be met. What should the project manager do A: Notify managemen B: Hold a team meetin C: Look for alternative ways to meet the quality leve D: Ask management tp come up with option