In your project, you are in the process of determining whether the activities being done as part of your project comply with organizational and project policies. This will be done as part of ______ .
A: A) inspection
B: B) quality audit
C: C) quality improvement
D: D) trend analysis
A: A) inspection
B: B) quality audit
C: C) quality improvement
D: D) trend analysis
举一反三
- You are assigned as a project manager to lead a new quality improvement project. Management is asking for a project management plan. Which of the following should you create FIRST A: A) A process assurance plan. B: B) A quality management plan. C: C) A project management plan. D: D) A project scope statement.
- During project execution, a new ISO version of standard 9000 is issued. The project team meets with the quality department to determine how the standard will apply to the project. Which part of the quality process is this A: Quality analysi B: Quality assuranc C: Quality contro D: Quality plannin
- 中国大学MOOC: In the __________ of proposals, you should demonstrate the need for the project, your qualifications for tackling the project, and your clear understanding of what needs to be done and how t
- In risk response planning,you are in the process of developing options,and determining actions to reduce threats to your project's objectives.When you show the results of your risk response planning to your project sponsor,she is not comfortable with the risks in the project and she suggests that the project scope should be decreased.This is an example of (). A: inappropriate risk management because it is having a direct impact on your project scope B: risk avoidance C: risk mitigation D: risk transfer
- In risk response planning,you are in the process of developing options,and determining actions to reduce threats to your project’s objectives.When you show the results of your risk response planning to your project sponsor,she is not comfortable with the risks in the project and she suggests that the project scope should be decreased.This is an example of______. A: inappropriate risk management because it is having a direct impact on your project scope B: risk avoidance C: risk mitigation D: risk transfer