• 2022-06-07
    You prepared an integrated project plan and a project schedule.You submitted it to the steering committee,and it was approved.Key stakeholders accepted the plan.It is time to distribute it.Both the project plan and schedule should be distributed to______.
    A: all stakeholders in the performing organization
    B: all project stakeholders
    C: project team members and the project sponsor
    D: people noted in the communications management plan