All of followings should be done by the project manager during project control except ______.
A: Determine the a change has occurred
B: Ensure that a change is agreed
C: Make sure all changes are approved by management
D: Manage changes as they occur
A: Determine the a change has occurred
B: Ensure that a change is agreed
C: Make sure all changes are approved by management
D: Manage changes as they occur
举一反三
- When should the project baseline be changed A: A) It should not he changed. B: B) Only for changes that have been approved by the change control board. C: C) At each project team meeting. D: D) For all implemented changes.
- The project team has created a plan for how they will implement the quality policy. If this changes during the project, it will also be a change to ______. A: the project plan B: the quality control plan C: the quality assurance plan D: the quality management plan
- Project manager believes that modifying the project scope may provide added value for the customer.the project manager should(). A: change the scopr baseline B: contact the customer to determine if the change adds value C: call a meeting of the change control board D: change the project's objectives
- Which of the followings is far from Integrated Change Control A: A) Influencing the factors that create change to ensure that changes are agreed upon. B: B) Determining that a change has occurred. C: C) Ensuring the integrated performance baseline doesn't change. D: D) Managing the actual changes when and as they occur.
- The project is not going well and many changes are being made. Which of the following should you do FIRST to gain control of the project ?() A: Review the scope of work with the stakeholders B: Create a new change form C: Remind everyone of the change procedures D: Ask management for help