In the project plan development, an example of a project constraint may be______.
A: a lump-sum contract
B: a project whose budget is still in the preliminary stages
C: the use of historical data as applied to the new project
D: a list of assumptions
A: a lump-sum contract
B: a project whose budget is still in the preliminary stages
C: the use of historical data as applied to the new project
D: a list of assumptions
举一反三
- From the macro to the micro level, the project plan does not include (). A: project development plan B: subject policy plan C: project strategic plan D: subject specific plan
- (9) are individuals and organizations that are actively involved in the project, or whose interests may be affected as aresult of project execution or project completion, they may also exert influence over the project and its results. A: Controls B: Baselines C: Project stakeholders D: Project managers
- The project life-cycle can be described as ( ). A: project concept, project planning, project execution, and project close-out B: project planning, work authorization,and project reporting C: project planning, project control, project definition, WBS development , and project termination D: project concept,project execution, and project reporting
- A project manager has just been assigned to a new project and has been given the project charter. The FIRST thing the project manager must do is______. A: A) create a project scope statement B: B) confirm that all the stakeholders have had input into the scope C: C) analyze project risk D: D) begin work on a project management plan
- You prepared an integrated project plan and a project schedule.You submitted it to the steering committee,and it was approved.Key stakeholders accepted the plan.It is time to distribute it.Both the project plan and schedule should be distributed to______. A: all stakeholders in the performing organization B: all project stakeholders C: project team members and the project sponsor D: people noted in the communications management plan