The project is not going well and many changes are being made. Which of the following should you do FIRST to gain control of the project
A: A) Review the scope of work with the stakeholders.
B: B) Create a new change form.
C: C) Remind everyone of the change procedures.
D: D) Ask management for help.
A: A) Review the scope of work with the stakeholders.
B: B) Create a new change form.
C: C) Remind everyone of the change procedures.
D: D) Ask management for help.
举一反三
- The project is not going well and many changes are being made. Which of the following should you do FIRST to gain control of the project A: A) Review the scope of work with the stakeholders. B: B) Create a new change form. C: C) Remind everyone of the change procedures. D: D) Ask management for help.
- You are assigned as a project manager to lead a new quality improvement project. Management is asking for a project management plan. Which of the following should you create FIRST A: A) A process assurance plan. B: B) A quality management plan. C: C) A project management plan. D: D) A project scope statement.
- A project manager has just been assigned to a new project and has been given the project charter. The FIRST thing the project manager must do is______. A: A) create a project scope statement B: B) confirm that all the stakeholders have had input into the scope C: C) analyze project risk D: D) begin work on a project management plan
- All of followings should be done by the project manager during project control except ______. A: Determine the a change has occurred B: Ensure that a change is agreed C: Make sure all changes are approved by management D: Manage changes as they occur
- Project manager believes that modifying the project scope may provide added value for the customer.the project manager should(). A: change the scopr baseline B: contact the customer to determine if the change adds value C: call a meeting of the change control board D: change the project's objectives