A project manager has made a change to the project. What should he do next
A: A) Assign resource.
B: B) Revise the project plan.
C: C) Evaluate impact.
D: D) Request change control board involvement.
A: A) Assign resource.
B: B) Revise the project plan.
C: C) Evaluate impact.
D: D) Request change control board involvement.
举一反三
- Project manager believes that modifying the project scope may provide added value for the customer.the project manager should(). A: change the scopr baseline B: contact the customer to determine if the change adds value C: call a meeting of the change control board D: change the project's objectives
- The project team has created a plan for how they will implement the quality policy. If this changes during the project, it will also be a change to ______. A: the project plan B: the quality control plan C: the quality assurance plan D: the quality management plan
- All of followings should be done by the project manager during project control except ______. A: Determine the a change has occurred B: Ensure that a change is agreed C: Make sure all changes are approved by management D: Manage changes as they occur
- You are assigned as a project manager to lead a new quality improvement project. Management is asking for a project management plan. Which of the following should you create FIRST A: A) A process assurance plan. B: B) A quality management plan. C: C) A project management plan. D: D) A project scope statement.
- You are assigned as the project manager in the middle of the project. The project is within the baselines, but the customer is not happy with the performance of the project. What is the FIRST thing you should do () A: Discuss it with the project team. B: Recalculate baselines. C: Renegotiate the contract. D: Meet with the customer.