- The inputs of developing project management plan do not include(). A: project charter B: stakeholder management strategy C: project scope statement D: outputs from plamung processes
- The process is primarily concerned with authorizing the project or, in a multiphase project, a project phase is called ______ . A: develop project charter B: develop prepliminary project scope statement C: management review D: phase-end review
- A project manager has just been assigned to a new project and has been given the project charter. The FIRST thing the project manager must do is______. A: A) create a project scope statement B: B) confirm that all the stakeholders have had input into the scope C: C) analyze project risk D: D) begin work on a project management plan
- You prepared an integrated project plan and a project schedule.You submitted it to the steering committee,and it was approved.Key stakeholders accepted the plan.It is time to distribute it.Both the project plan and schedule should be distributed to______. A: all stakeholders in the performing organization B: all project stakeholders C: project team members and the project sponsor D: people noted in the communications management plan
- The project plan is used to do all of the following EXCEPT ______. A: A) document project planning assumption B: B) define the content of management reviews C: C) identify risks that arise during project execution D: D) provide a baseline for progress measurement and project control
内容
- 0
The close project process is a part of which of the following project management knowledge areas ?() A: project scope managemen B: project integration managemen C: project time managemen D: project communication managemen
- 1
The project team has created a plan for how they will implement the quality policy. If this changes during the project, it will also be a change to ______. A: the project plan B: the quality control plan C: the quality assurance plan D: the quality management plan
- 2
The project charter is created in which project management process group ?() A: Executing B: Planning C: Closing D: Initiating
- 3
● (74) is primarily concerned with defining and controlling what is and is not included in the project. (74) A. Project Time Management B. Project Cost Management C. Project Scope management D. Project Communications Management
- 4
You are assigned as a project manager to lead a new quality improvement project. Management is asking for a project management plan. Which of the following should you create FIRST A: A) A process assurance plan. B: B) A quality management plan. C: C) A project management plan. D: D) A project scope statement.